JCPSG | TRAC Guidance
Part V - TRAC fEC
Section F: Post-award
Recording costs
- The costs incurred on each project should be recorded.
- DI costs should be recorded as the actual expenditure
is incurred. This is the case even when the actual costs exceed the original
DI level (and might therefore be ineligible for funding). However, costs
recorded in the DI category should be DI costs. In particular,
the recording of maternity, paternity and paid sick leave depends on their
classification:
- for RAs and staff in the directly incurred category of cost, they are
DI costs. Sponsors generally allow virement within DI costs, and will often
consider funding them even if it means that the original DI estimate is exceeded;
- for academics, they are indirect costs. Investigators are classified as
a DA cost, and charge-out rates are applied. These are based on the direct
salaries (and on-costs) of staff, and incorporate assumptions about the working
year and the time spent on direct Research activity. These do not include
payments or time for any maternity, paternity or sick leave. The costs of
these have been built into the indirect cost rates (part of the Support time
and cost). Therefore, if incurred for a PI on a particular project, those
costs should be allocated to Support in the annual TRAC process and should
not be recorded as a direct project cost in TRAC fEC.
- DA and indirect costs can be recorded on original estimate. This provides
a relatively simple method of recording the fEC of each project each year.
- Changes to indirect cost rates, or charge-out rates, or the level of resources
being charged as DA costs, need not be recorded against the project cost
record.
- If institutions wish, they can amend their DA and indirect cost charges
to reflect more up-to-date rates, or indices, or perhaps actual estates utilisation,
for example. However, any recorded increase in DA and indirect costs (from
the original indexed estimates) will not lead to additional funding by most
sponsors.
- For example, changes in the Research Assistant staffing could theoretically
lead to different levels of PI, estates and indirect costs. If two RAs are
budgeted (i.e. estimated in the bid), one leaves early, and then two new
appointments are made, funders such as the Research Councils would not recognise
any differences in the PI, estates or indirect cost totals charged to the
project from those originally estimated.
- However, any decrease in DA and indirect costs recorded or reported against
a project may lead to a lower funding, as public bodies have an obligation
to ensure that their funds are being used for the purpose originally agreed.
- Most fEC-based funders will only change their price where there is a substantial
change to the programme of work (e.g. departure of a key member of staff
early in the project; serious curtailment of the work; or significant change
to the type of work being undertaken). Except in these instances, there is
no requirement under TRAC to change DA or indirect cost estimates during
the project life.
- Where a project transfers to another institution, it is good practice
for the recipient institution to recalculate the costs on the project. However,
this would only be done if the difference is likely to be significant, and
if the institution has systems that allow them to make this calculation efficiently.
Changes to funding are not likely to follow – see for example Research
Councils’ policies, given on their website, accessible from
Annex
1.
- Rolling programmes more than three years in length are generally subject
to a mid-term scientific review, at which time they may be extended. In these
cases, the costs estimates (and prices) should be reviewed
at this time.
- The estimates being recorded each year should be updated
for the relevant price level. This can be based on the original phasing of
estimates at project approval stage and the original indices.
- Entries should be made in project cost records once the
work has started. For DI costs this will be when they start to be incurred.
For DA and indirect costs this could be when the DI costs start to be incurred,
when the investigator starts work, or when the sponsor recognises these costs
for funding. It may be easier for institutions to use the latter, so that
their costing and invoicing/income receivable systems are compatible.
- The Research Councils, for example, allow expenditure to be incurred prior
to the start of the research, and subsequently charged to the grant, provided
it does not precede the date of the award letter. Payments, however, take
effect from the notified start date (shown on the starting certificate) or,
if staff are being appointed, from the date when the first such staff start
work.
- The recording fields, and periods, should be those that
are most useful to the institution for managing the projects, charging sponsors,
recording debtors, and making reconciliations at year-end and project-end.
Quarterly or monthly records may be appropriate; but records should be
made on a regular basis.
Reporting costs
- Project fEC-based costs will be reported:
- to sponsors, in accordance with their requirements – the Research
Councils, for example, require an Expenditure Statement at the end of a
research grant;
- as part of the external QA arrangements – the records required
for this are described under verification, below;
- possibly, at an aggregated level, to HESA FSR – see
Annex
1.
- The categories of costs currently reported as the direct costs of research
to the Higher Education Statistics Agency (HESA) in the Finance Statistics
Return (FSR) are not being changed, for the time being. In this context note:
- direct costs as currently defined would be reported (covering RAs, consumables,
etc.), but neither estates charges nor PI salaries would be reported as direct
costs of Research for the purposes of this return;
- the FSR is based on the financial statements, which do not include the
TRAC cost adjustments. Direct costs will, anyway, only be partially funded
by the Research Councils. There may be issues of confidentiality. HESA definitions
are likely to need reviewing as a result of TRAC;
- research income on cost-based projects such as for the Research Councils
may currently be defined for HESA with reference to costs. In this case a
simple x% of recorded fEC could be used to establish Research Council income.
- Project cost records (maintained during the life of each project) might
also be required to meet the needs arising from:
- resource allocation (perhaps to identify the income from projects that
academics are entitled to spend);
- the identification of income receivable/income received in advance;
- the requirement to compare charges made to Research Council projects in
any one year for academics’ costs (through the standard charges recorded
on project cost records), with the costs of the time they have actually spent
(through the annual TRAC time allocation process);
- other information (e.g. confirming whether the total level of directly
allocated charges made during a year for an area of cost, such as a research
facility, have been set at a level that appropriately ensures the recovery
of those costs).
- However, project cost records are not required for the preparation of
financial statements.
Verifying costs
- The costs estimated on projects should be verified, to
ensure that they were actually incurred.
- Verification can be done by either:
- recording actual costs as incurred; or
- recording costs on estimate, and then matching these with the original
rate calculations.
- Unless otherwise specified below, the required records should be
kept at project level on systems that (a) provide an audit trail; and (b)
allow aggregation of the entries in each field (time or cost category) each
year. The total cost should be recorded in all cases (not
any lesser total that forms the price for a particular sponsor).
- Directly incurred costs, such as RAs, dedicated technicians and other
staff, consumables, travel and subsistence, and purchases of equipment for
a project, should be recorded as expenditure is made, according
to current practice.
- Directly allocated costs, such as pool/shared technicians, major research
facilities, and estates, should be charged against the project,
on a periodic basis (at least annually) according to estimated usage (by
way of regular recharge journal or similar). The original records of estimated
usage for Research, and calculation of the rates being applied, should be
available for audit on an appropriate project file (but this could be paper-
or electronic-based).
- The costs of PIs, fellows and co-investigators, as originally estimated
and finalised during the project application process, should be
recorded against the project periodically, not less than once a year. Again,
appropriate records of the time originally estimated, and the pay bandings
applied, should be available for audit on an appropriate
project file (but the time estimated need not be in a form that could be
aggregated for all projects, although this would be good practice).
- Indirect costs should be periodically recorded on initial
estimate, not less than once a year. Appropriate records of the time and
rates used to calculate the indirect cost totals should be
kept for audit, but this could be a paper- or electronic-based file.
- Each year, or as required for project management purposes, the Principal
Investigator should be able to confirm (or otherwise) that,
broadly, the amount of time estimated at the start of the project is likely
to have been spent, and will be spent, by the staff on the project. Broadly,
in this context, means cumulative over the project so far, with reasonable
assumptions as to future work on the project, and plus or minus 20%.
- The PI should be in a position to confirm this; the institution
or head of department need not take responsibility, unless the institution
so wishes. The PI need not keep formal records – but sponsors’ ‘dipstick’ style
visits might need to see some evidence of time spent, e.g. paper-based diary
entries, records of meetings, volume/quality of outputs, laboratory notes,
conflicts of time flagged with head of department or supervisor, and so on.
This does not imply the need for any timesheets, but it
would be good practice in project management to keep a simple record (e.g.
in a desk diary) of the significant inputs made to the project. The events,
rather than time, are all that might be recorded in
this. See
Annex 1 – Research
Council website – for more information on Research Council dipstick
testing.
- The records therefore required under TRAC are no more than the desk diaries,
laboratory notebooks and other mechanisms that staff already use to manage
their time and their projects.
- Timesheets or other records of actual academic staff time by project should
not be maintained to meet TRAC requirements. They are not required
under TRAC. However, if a research unit does decide to complete partial
or full timesheets (perhaps to satisfy EU or commercial requirements; or
to overcome problems of robustness if there is little Research activity),
then institutions should ensure that those processes,
including the definitions of hours and costs/hour, are broadly compatible
with the processes institutions are introducing more widely, both for project
costing under TRAC and for the annual TRAC cost allocation exercise.
- Exceptionally, the Research Councils may require special project management
procedures on very large projects, as currently (e.g. ESRC centres). This
might continue to involve a particular type of time-recording (such as timesheets).
- Every year, from 2009, the institutions should compare
the total academic costs attributed to the Research Council sponsor group
in the annual TRAC time allocation exercise, with the total academic staff
costs charged to Research Council projects in the accounting records - see reconciliation.