|
|
Part IV - Other charge-out rates
Section G: Other Charge-out rates
Chapter G.2 Major research facilities
- The cost of equipment, including major research facilities, should be
directly allocated to research projects. This means that it should
not appear in the indirect cost rate. Equipment costs are
to be included in the estates costs total, but no later than 1 August 2007
major research facilities should be directly allocated to
research projects separately from the estates charge.
- It is good practice for other equipment to be directly allocated separately
from estates as well, but that is not a minimum requirement. Materiality
is an important consideration.
- All reference to a research facility in this chapter could also refer to
equipment. A research facility can be a single piece of equipment,
or a group of equipment.
- Major research facilities include specialist animal facilities, greenhouses,
and specialist IT research facilities.
- The charge-out rate for a research facility should be established by the
following calculation:
an annual fEC (a)
total units of use for a year (b);
a charge-out rate per unit of use: (a) divided by (b).
- The charge-out rate should then be applied to projects
based on an estimate of the units used by each of
those projects.
- The calculation of the rate, and the data collected for this purpose, should avoid
undue complexity or spurious accuracy. It is not necessary
to know either the historical cost or the sponsor of a piece of equipment
when charging it directly onto projects. The avoidance of double-charging
is covered further on in this
chapter.
Annual fEC (a)
- The annual fEC should include an estimate of the following
costs, where applicable:
- depreciation (based on an estimate of its replacement cost, written off
over the likely useful life of the equipment). This would take into
account exceptional procurement costs, installation costs, buildings modification,
set-up and testing;
- technicians;
- consumables and spares;
- additional insurance;
- estates.
- The operating costs (consumables, spares etc.) can be based on the actual
costs of running that facility or a forecast level of costs.
- The costs of technicians and consumables should only be
included where they are not being included as a directly incurred cost on
any other project, and are excluded from the laboratory technician charge-out
rate.
- Estates costs need not be included for all facilities – only where
material.
- Indirect costs should not be included.
- The annual fEC (a) should include a depreciated replacement
cost for the equipment (a broad estimate would suffice if detailed records
are not available) written off over the likely useful life of the equipment. This
replacement cost is unlikely to be the same as the historic cost.
- This replacement cost should be included irrespective
of who funded its original purchase, when, and at what price.
Likely use of the facility (b)
- The likely use of the equipment (b) should be estimated. This
should take into account its use for all activities (including Teaching)
by all projects (including institution-/own-funded work and supervision of
PGR students) and by all academics and all departments. This utilisation
would commonly be expressed in terms of units of time (e.g. days or hours
of use per year).
- Utilisation should be calculated on the assumption of
at least a ‘reasonably efficient’ basis (in the context of use
in the HE sector). If institutions plan higher utilisation than this,
then those higher estimates of time should be included. The
calculation of utilisation should therefore take into account
the likely use (days or hours) of each facility for Teaching, Research (including
all of institution-/own-funded, PGR supervision, external projects), and
Other activities; but should also include additional days
or hours if this likely use is significantly less than a level normally experienced
in the sector for this type of facility.
- ‘Reasonably efficient utilisation’ which is normal for the
sector could be established having considered:
- utilisation that provides a market charge-out rate for this type of kit;
- a concept of ‘well-managed equipment’; or
- the target utilisation for the equipment (as long as it was not too light).
Calculation of the charge-out rate
- The annual fEC (a) divided by the units of use (b) provides the charge-out
rate for that item of equipment. If equipment has been grouped in this
calculation, but each item of equipment can be used separately on projects,
then the group charge out rate should be divided by the
number of items of equipment to give a rate per item of equipment. (Weightings
could be used in this but not if these make the calculation unduly complex.)
- Each project’s use of each item of equipment should then
be estimated, e.g. in terms of days or hours of use. Again, undue complexity
should be avoided: standards can be developed and applied. The
relevant charge-out rate for the items of equipment used should then
be applied to that time. This then provides a directly allocated cost
for inclusion in the fEC of each project (and into the costs of Teaching,
institution-/own-funded Research and PGR supervision when costed).
- The charge-out rates should be indexed, along with all
other costs, over the life of the project. Rates calculated on 1 February
each year should be indexed for two years’ price rises,
before they are applied to a research project application.
Animal houses
- Animal houses should be considered a major facility:
- the purchase of animals should be a DI cost (and if the number actually purchased is less than or more than originally estimated, the actual DI costs will change);
- surgical procedures or other costs that are purchased from external sources specifically for a project should be charged as DI;
- other costs, in particular housing, maintenance and operating costs, should
be DA costs, charged to projects using charge-out rates.
- The DA costs should include:
- estates costs of the defined space housing the facility;
- facility manager, laboratory technicians, other administrative staff, veterinary services including surgical procedures when not externally purchased;
- bedding and feed;
- other operating, maintenance and support costs.
These costs should not be included in the estates or indirect cost rates, or charged as a DI cost.
- A number of charge-out rates should be calculated and applied to projects – these would vary
depending upon the type of:
- animal;
- condition;
- care/maintenance provided.
 |

|
|
This page last updated
© HEFCE 2005 The copyright for this publication is held by the Higher Education
Funding Council for England (HEFCE). The material may be copied or
reproduced provided that the source is acknowledged and the material,
wholly or in part, is not used for commercial gain. Use of the material
for commercial gain requires the prior written permission of HEFCE.
|
|